Glider Project Deployed Recovered Days Distance Start/
End Voltage
Air Time POC Notes Payload KMZs Data Metadata
ru24-263 LTER 2012-01-24
18:53 GMT
2012-01-30
18:18 GMT
5.98 47.8
km
15.18 Volts
12.31 Volts
836
minutes
Haskins
Miles
Aragon
14 0139 kmzs

deployment Notes (14)  

Select Category: Deployment Glider All

Posted/
Updated
Category
2012-01-31 01:36 GMT
dkaragon
deployment Recovered by Travis Miles out of Palmer Station.
2012-01-30 16:23 GMT
dkaragon
deployment u_min_water_depth 0
2012-01-30 13:33 GMT
dkaragon
2012-01-30 13:33 GMT
dkaragon
deployment Leaving FIre on since I think recover is imminent.
Retasked to station E an 1 hour missions
2012-01-29 01:54 GMT
dkaragon
deployment Fire On
2012-01-27 20:09 GMT
dkaragon
deployment Trying to figure out why PAR from fire is 0, turned on sensor at the surface:

15917 63 science wrote:sci_FIRe_timestamp(timestamp) 1327694855.002
15917 science wrote:sci_FIRe_Fo(nodim) 32.3125877380371
15917 science wrote:sci_FIRe_Fm(nodim) 28.4218616485596
15917 science wrote:sci_FIRe_FvFm(nodim) -0.136891946196556
15917 Sent science:s:m_cycle_number(nodim) 3463-
15918 science wrote:sci_FIRe_s(nodim) -0.0704262107610702
15918 science wrote:sci_FIRe_p(nodim) 0.309925317764282
15918 science wrote:sci_FIRe_par(nodim) Inf
15918 science wrote:sci_FIRe_battery(volts) 12.3210144042969
15918 science wrote:sci_FIRe_temp(degC) 0
15918 science wrote:sci_FIRe_frame_count(nodim) 16
2012-01-27 18:51 GMT
dkaragon
deployment Fire is off as of last surfacing.

Confirmed that state 7 does not cause the abort of science not shutting down properly.
2012-01-27 01:47 GMT
dkaragon
deployment Fire ON
2012-01-26 13:21 GMT
dkaragon
deployment Fire OFF
2012-01-26 02:33 GMT
dkaragon
deployment Fire ON
2012-01-25 13:29 GMT
dkaragon
deployment Fire OFF
2012-01-25 02:33 GMT
dkaragon
deployment Fire ON, state 7 (not at surface)
2012-01-24 20:50 GMT
haskins
deployment Increased yo10 from 55m to 97m and increased surfac20 from 1hour to three hour missions.
2012-01-24 19:37 GMT
haskins
deployment Deployed by Travis Miles and Crew East of Station E. Shore support by Haskins.

RU24 was given RU06's goto. RU24 will be deployed for the next 4-5 days until RU06 is recovered.
2012-01-24 19:36 GMT
haskins
configuration Payload Bay 139 with FIRe sensor.